October 8, 2022 – Ride-on Activities

October 8, 2022 – Ride-on Activities

Updates:

When: October 8, 2022

What: BLCI facilitated ride-on activities during the NGCP Scheduled Power Interruption from 6:00am – 6:00pm

a. Erection of steel pole at BLCI Poblacion Substation in preparation for the additional 20-MVA Substation Project.

b. Stringing of 3-phase primary line from MMG Coop Hospital going to Divine Mercy Chapel.

For your information and guidance.

Thank you.